- Drilling for our shoring system continues as scheduled
- Drilling for our shoring system continues as scheduled
- A second drilling machine has been brought on site to increase the number of holes drilled per day
- Drilling for our shoring system continues as scheduled, including drilling of the final hole for 2019!
- Drilling for our shoring system continues as scheduled
- Drilling for our shoring system continues as scheduled
- Drilling for our shoring system continues as scheduled
- Drilling for our shoring system continues as scheduled
- Shoring has begun, starting at the north-west corner of the site
- Three to four caissons will be drilled and poured per day
- Shoring is expected to last for approximately four months
- Progress continues on preparation of the site for shoring and excavation
- Progress continues on preparation of the site for shoring and excavation