- Continuing to pour the outside walls.
- Steel work continues on the elevator shaft
- Preparing to pour P4 Slab
RP Update 50
- Stones are being poured into the site, they will be under the P4 Slab
- Drains under the building its being installed.
- Continuing to pour outside walls
- Steel work on the Elevator shaft is continuing
Kingsway Update 6
Condo
- Excavation Continues
- Dewatering system install
- Lagging Underway


Rentals
- Shoring is continuing
- Tiebacks have been completed
- Stressing of tiebacks to begin
- Bulking 118 elevation to continue
Rp Update 49
- Crane Pad is being poured.
- Preparation for crane to be erected.
- Steel being laid for foundation walls.
- Continuing to p0ur columns.
RP Update 49
- Steel for Crane Pad is ready
- Crane Pad to be poured
- Crane to be erected
RP Update 48
- Water Proofing being completed for the crane pad.
- Pouring columns
- Preparing Steel for the Crane Pad
RP Update 47
- Water Proofing being completed on the lowest level.
- Steel being tied on the walls.
- Setting up for pouring columns
RP Update 46
- Excavation has been completed.
RP Update 45
- We are now one week away from completing our excavation.
- Waterproofing of the site has now begun and will continue for the 3 – 4 months,
- Construction of footings has now also begun, along with the early stages of the building foundation.
RP Update 44
- Excavating and shoring continue as scheduled.
- Our mobile crane has now been delivered and is operating on site.