Skip to content

293 Kingsway

Just another WordPress site

RP Update 51

  • Continuing to pour the outside walls.
  • Steel work continues on the elevator shaft
  • Preparing to pour P4 Slab
Posted byadminSeptember 14, 2020Posted inRedpathLeave a comment on RP Update 51

RP Update 50

  • Stones are being poured into the site, they will be under the P4 Slab
  • Drains under the building its being installed.
  • Continuing to pour outside walls
  • Steel work on the Elevator shaft is continuing

Posted byadminSeptember 7, 2020September 14, 2020Posted inRedpathLeave a comment on RP Update 50

Kingsway Update 6

Condo

  • Excavation Continues
  • Dewatering system install
  • Lagging Underway

Rentals

  • Shoring is continuing
  • Tiebacks have been completed
  • Stressing of tiebacks to begin
  • Bulking 118 elevation to continue
Posted byadminAugust 24, 2020Posted inKingswayLeave a comment on Kingsway Update 6

Rp Update 49

  • Crane Pad is being poured.
  • Preparation for crane to be erected.
  • Steel being laid for foundation walls.
  • Continuing to p0ur columns.

Posted byadminAugust 24, 2020October 1, 2020Posted inRedpathLeave a comment on Rp Update 49

RP Update 49

  • Steel for Crane Pad is ready
  • Crane Pad to be poured
  • Crane to be erected

Posted byadminAugust 17, 2020August 24, 2020Posted inRedpathLeave a comment on RP Update 49

RP Update 48

  • Water Proofing being completed for the crane pad.
  • Pouring columns
  • Preparing Steel for the Crane Pad
Posted byadminAugust 10, 2020August 24, 2020Posted inRedpathLeave a comment on RP Update 48

RP Update 47

  • Water Proofing being completed on the lowest level.
  • Steel being tied on the walls.
  • Setting up for pouring columns
Posted byadminAugust 3, 2020August 24, 2020Posted inRedpathLeave a comment on RP Update 47

RP Update 46

  • Excavation has been completed.
Posted byadminJuly 27, 2020August 21, 2020Posted inRedpathLeave a comment on RP Update 46

RP Update 45

  • We are now one week away from completing our excavation.
  • Waterproofing of the site has now begun and will continue for the 3 – 4 months,
  • Construction of footings has now also begun, along with the early stages of the building foundation.
Posted bychrisJuly 20, 2020July 21, 2020Posted inRedpathLeave a comment on RP Update 45

RP Update 44

  • Excavating and shoring continue as scheduled.
  • Our mobile crane has now been delivered and is operating on site.
Posted bychrisJuly 13, 2020July 21, 2020Posted inRedpathLeave a comment on RP Update 44

Posts navigation

Newer posts 1 2 3 4 5 6 … 9 Older posts

Recent Posts

  • Kingsway Update
  • 71 Redpath August Update
  • 293 Kingsway Condos
  • July Update
  • June Update

Recent Comments

    Archives

    • August 2021
    • July 2021
    • June 2021
    • May 2021
    • April 2021
    • March 2021
    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • August 2020
    • July 2020
    • June 2020
    • May 2020
    • April 2020
    • March 2020
    • February 2020
    • January 2020
    • December 2019
    • November 2019
    • October 2019
    • September 2019

    Categories

    • Kingsway
    • Redpath
    • Uncategorized

    Meta

    • Log in
    • Entries feed
    • Comments feed
    • WordPress.org
    293 Kingsway, Proudly powered by WordPress.