- Pouring first section of P1
- Finishing steelworks on P1 on far side
- Completing waterproofing on P1 exterior walls.
Redpath update 65
- Steel work being finished for P1
- Waterproofing exterior P1 walls
- Elevator core being poured.
Redpath update 64
- Steel work for P1 continuing
- Decking for P1 being put up
- Exterior walls being poured for P2
Redpath Update 63
- Steel work for P1 is in progress
- Preparation for pouring P1
- In process of pouring P2 Exterior walls and columns
Redpath Update 62
- Waterproofing P2 exterior walls
- Completing pouring P2
- Starting to deck for P1
- Preparing for P2 exterior walls after waterproofing
Redpath Update 61
- Pouring P3 exterior walls, and columns
- Preparing to pour P2
- Decking for P1 to go up in preparation for steel work
Redpath update 60
- P3 ramp has been completed
- Steel work continues for P2
- Preparing to pour P2
Kingsway Update 11
Condo
- Temporary ramp to be completed.
- Crane Pad to be dug
- Continuing to haul out spoils
Rental
- Beginning underground drainage for Building B
- Pouring Elevator and Stair Pad for Building B
- Building A Stair Pad and Elevator to be dug out.
Kingsway Update 10
Condo
- Continuing to haul out soil.
- Crane Pad to be installed in preparation.

Rentals
- Continuing concrete footings and columns for Building A.
- The Crane for Building A has been Erected.
- Beginning underground drains on building B.
- Digging elevator footing on Building B.
Redpath Update 59
- Large section of P3 have been poured
- Continuing to waterproof P3 walls
- Decking for P2 is in the process of being erected