Skip to content

293 Kingsway

Just another WordPress site

Redpath Update 66

  • Pouring first section of P1
  • Finishing steelworks on P1 on far side
  • Completing waterproofing on P1 exterior walls.
Posted byadminJanuary 11, 2021January 25, 2021Posted inRedpathLeave a comment on Redpath Update 66

Redpath update 65

  • Steel work being finished for P1
  • Waterproofing exterior P1 walls
  • Elevator core being poured.
Posted byadminDecember 21, 2020January 25, 2021Posted inRedpathLeave a comment on Redpath update 65

Redpath update 64

  • Steel work for P1 continuing
  • Decking for P1 being put up
  • Exterior walls being poured for P2
Posted byadminDecember 14, 2020January 25, 2021Posted inRedpathLeave a comment on Redpath update 64

Redpath Update 63

  • Steel work for P1 is in progress
  • Preparation for pouring P1
  • In process of pouring P2 Exterior walls and columns
Posted byadminDecember 7, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath Update 63

Redpath Update 62

  • Waterproofing P2 exterior walls
  • Completing pouring P2
  • Starting to deck for P1
  • Preparing for P2 exterior walls after waterproofing
Posted byadminNovember 30, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath Update 62

Redpath Update 61

  • Pouring P3 exterior walls, and columns
  • Preparing to pour P2
  • Decking for P1 to go up in preparation for steel work
Posted byadminNovember 23, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath Update 61

Redpath update 60

  • P3 ramp has been completed
  • Steel work continues for P2
  • Preparing to pour P2
Posted byadminNovember 16, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath update 60

Kingsway Update 11

Condo

  • Temporary ramp to be completed.
  • Crane Pad to be dug
  • Continuing to haul out spoils

Rental

  • Beginning underground drainage for Building B
  • Pouring Elevator and Stair Pad for Building B
  • Building A Stair Pad and Elevator to be dug out.
Posted byadminNovember 16, 2020July 23, 2021Posted inKingswayLeave a comment on Kingsway Update 11

Kingsway Update 10

Condo

  • Continuing to haul out soil.
  • Crane Pad to be installed in preparation.

Rentals

  • Continuing concrete footings and columns for Building A.
  • The Crane for Building A has been Erected.
  • Beginning underground drains on building B.
  • Digging elevator footing on Building B.
Posted byadminNovember 9, 2020November 9, 2020Posted inKingswayLeave a comment on Kingsway Update 10

Redpath Update 59

  • Large section of P3 have been poured
  • Continuing to waterproof P3 walls
  • Decking for P2 is in the process of being erected
Posted byadminNovember 9, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath Update 59

Posts navigation

Newer posts 1 2 3 4 … 9 Older posts

Recent Posts

  • Kingsway Update
  • 71 Redpath August Update
  • 293 Kingsway Condos
  • July Update
  • June Update

Recent Comments

    Archives

    • August 2021
    • July 2021
    • June 2021
    • May 2021
    • April 2021
    • March 2021
    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • August 2020
    • July 2020
    • June 2020
    • May 2020
    • April 2020
    • March 2020
    • February 2020
    • January 2020
    • December 2019
    • November 2019
    • October 2019
    • September 2019

    Categories

    • Kingsway
    • Redpath
    • Uncategorized

    Meta

    • Log in
    • Entries feed
    • Comments feed
    • WordPress.org
    293 Kingsway, Proudly powered by WordPress.