Drilling for our shoring system continues as scheduled
Category Archives: Redpath
RP Update 13
Drilling for our shoring system continues as scheduled
RP Update 12
Drilling for our shoring system continues as scheduled
RP Update 11
Shoring has begun, starting at the north-west corner of the site Three to four caissons will be drilled and poured per day Shoring is expected to last for approximately four months
RP Update 10
Progress continues on preparation of the site for shoring and excavation
RP Update 9
Progress continues on preparation of the site for shoring and excavation
RP Update 8
Progress continues on preparation of the site for shoring and excavation
RP Update 7
To prepare for shoring, a layer of topsoil is being removed from our site and replaced with shale Shoring is scheduled to begin first thing next week
RP Update 6
New fencing has been erected around our site, including a delineation setting the boundaries of our onsite parkland dedication The site is now being prepared for the shoring drilling equipment
RP Update 5
Demolition is now complete Shale is being brought onsite to backfill the voids left from demolishing the house foundations Once all backfilling is complete, the site will be graded in preparation for the beginning of shoring