293 Kingsway Condo Update The parking levels are now complete. The Ground floor walls and columns are in place and 50% of the deck on the ground floor is also complete. The Kingsway Rentals Kingsway Rental Building A ground floor is complete and the 2nd floor deck is to be poured next week. Concrete for […]

Kingsway Update 7

293 The Kingsway ProgressVertical shoring is completeTieback installation has started Site excavation continues.  Add pics of these items crop and size photos Rental Building progressVertical Shoring and Tieback installation for the 2 rental buildings is complete. Concrete footings will be poured at the basement level during the week of September 14th.  Reinforcing steel for the basement foundation […]