Drilling for our shoring system continues as scheduled
Author Archives: chris
RP Update 19
Drilling for our shoring system continues as scheduled
RP Update 18
Drilling for our shoring system continues as scheduled
RP Update 17
Drilling for our shoring system continues as scheduled A second drilling machine has been brought on site to increase the number of holes drilled per day
RP Update 16
Drilling for our shoring system continues as scheduled, including drilling of the final hole for 2019!
RP Update 15
Drilling for our shoring system continues as scheduled
RP Update 14
Drilling for our shoring system continues as scheduled
RP Update 13
Drilling for our shoring system continues as scheduled
RP Update 12
Drilling for our shoring system continues as scheduled
RP Update 11
Shoring has begun, starting at the north-west corner of the site Three to four caissons will be drilled and poured per day Shoring is expected to last for approximately four months