Skip to content

293 Kingsway

Just another WordPress site

Author Archives: admin

RP Update 51

Continuing to pour the outside walls. Steel work continues on the elevator shaft Preparing to pour P4 Slab

Posted byadminSeptember 14, 2020Posted inRedpathLeave a comment on RP Update 51

RP Update 50

Stones are being poured into the site, they will be under the P4 Slab Drains under the building its being installed. Continuing to pour outside walls Steel work on the Elevator shaft is continuing

Posted byadminSeptember 7, 2020September 14, 2020Posted inRedpathLeave a comment on RP Update 50

Kingsway Update 6

Condo Excavation Continues Dewatering system install Lagging Underway Rentals Shoring is continuing Tiebacks have been completed Stressing of tiebacks to begin Bulking 118 elevation to continue

Posted byadminAugust 24, 2020Posted inKingswayLeave a comment on Kingsway Update 6

Rp Update 49

Crane Pad is being poured. Preparation for crane to be erected. Steel being laid for foundation walls. Continuing to p0ur columns.

Posted byadminAugust 24, 2020October 1, 2020Posted inRedpathLeave a comment on Rp Update 49

RP Update 49

Steel for Crane Pad is ready Crane Pad to be poured Crane to be erected

Posted byadminAugust 17, 2020August 24, 2020Posted inRedpathLeave a comment on RP Update 49

RP Update 48

Water Proofing being completed for the crane pad. Pouring columns Preparing Steel for the Crane Pad

Posted byadminAugust 10, 2020August 24, 2020Posted inRedpathLeave a comment on RP Update 48

RP Update 47

Water Proofing being completed on the lowest level. Steel being tied on the walls. Setting up for pouring columns

Posted byadminAugust 3, 2020August 24, 2020Posted inRedpathLeave a comment on RP Update 47

RP Update 46

Excavation has been completed.

Posted byadminJuly 27, 2020August 21, 2020Posted inRedpathLeave a comment on RP Update 46

RP Update 1

We will be beginning our demolition on September 23, 2019 We will be demolishing for approximately four weeks during which time the site will be fenced off for safety Dust mitigation and traffic control plans will be enforced

Posted byadminSeptember 18, 2019March 11, 2020Posted inRedpathLeave a comment on RP Update 1

Posts navigation

Newer posts 1 2 3 4

Recent Posts

  • Kingsway Update
  • 71 Redpath August Update
  • 293 Kingsway Condos
  • July Update
  • June Update

Recent Comments

    Archives

    • August 2021
    • July 2021
    • June 2021
    • May 2021
    • April 2021
    • March 2021
    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • August 2020
    • July 2020
    • June 2020
    • May 2020
    • April 2020
    • March 2020
    • February 2020
    • January 2020
    • December 2019
    • November 2019
    • October 2019
    • September 2019

    Categories

    • Kingsway
    • Redpath
    • Uncategorized

    Meta

    • Log in
    • Entries feed
    • Comments feed
    • WordPress.org
    293 Kingsway, Proudly powered by WordPress.