Torching out Corner Braces and Whalers Continuing the pour of P3 Preparation for P2 Columns and Exterior walls being poured for P3,P2
Author Archives: admin
Kingsway Update 9
Condo Beginning to dismantle dewatering system Continuing the cut to sub grade Rental Beginning backfill at interior footings on Building B Starting to pour footings for Building A Begging underground drain preparation for Building B Crane for Building A to be operational
RP Update 57
P3 pour continuing on site Working on exterior wall water proofing Continuing to lay steel for the completion of P3
Kingsway Update 8
Condo Lagging has Been Completed Soil Being Hauled out by Roni Rentals Building A Crane Pad to be poured Building A Dewatering set to be dismantled Concrete footings and columns underway at Building B
RP Update 56
All Slab on Grade plumbing has been completed Slab on grade has been completed Continuing to pour P3 Slab
RP Update 55
Preparing steel for first P3 pour Final P4 Pour to be completed Ramp to be poured for P3-P4
RP update 54
Pours continuing for P4 Slab. Slab on grade Drainage work continues. Decking and Preparation for P3 slab continues.
RP Update 53
Completed perimeter foundation wall. Completed all upright columns for the foundation. Decking is up on the south side of the site in preparation for P3. Continuing the pour for P4 slab.
RP Update 52
Formwork continues for the Elevator Shaft The south part of the P4 slab has been poured Continuing to pour the outside walls Stone is being used to fill below the P4 slab Drainage on the north part of the site is being placed.
Kingsway Update 7
293 The Kingsway ProgressVertical shoring is completeTieback installation has started Site excavation continues. Add pics of these items crop and size photos Rental Building progressVertical Shoring and Tieback installation for the 2 rental buildings is complete. Concrete footings will be poured at the basement level during the week of September 14th. Reinforcing steel for the basement foundation […]