Pouring first section of P1 Finishing steelworks on P1 on far side Completing waterproofing on P1 exterior walls.
Author Archives: admin
Redpath update 65
Steel work being finished for P1 Waterproofing exterior P1 walls Elevator core being poured.
Redpath update 64
Steel work for P1 continuing Decking for P1 being put up Exterior walls being poured for P2
Redpath Update 63
Steel work for P1 is in progress Preparation for pouring P1 In process of pouring P2 Exterior walls and columns
Redpath Update 62
Waterproofing P2 exterior walls Completing pouring P2 Starting to deck for P1 Preparing for P2 exterior walls after waterproofing
Redpath Update 61
Pouring P3 exterior walls, and columns Preparing to pour P2 Decking for P1 to go up in preparation for steel work
Redpath update 60
P3 ramp has been completed Steel work continues for P2 Preparing to pour P2
Kingsway Update 11
Condo Temporary ramp to be completed. Crane Pad to be dug Continuing to haul out spoils Rental Beginning underground drainage for Building B Pouring Elevator and Stair Pad for Building B Building A Stair Pad and Elevator to be dug out.
Kingsway Update 10
Condo Continuing to haul out soil. Crane Pad to be installed in preparation. Rentals Continuing concrete footings and columns for Building A. The Crane for Building A has been Erected. Beginning underground drains on building B. Digging elevator footing on Building B.
Redpath Update 59
Large section of P3 have been poured Continuing to waterproof P3 walls Decking for P2 is in the process of being erected