293 Kingsway Condo Update The parking levels are now complete. The Ground floor walls and columns are in place and 50% of the deck on the ground floor is also complete. The Kingsway Rentals Kingsway Rental Building A ground floor is complete and the 2nd floor deck is to be poured next week. Concrete for […]
Author Archives: admin
71 Redpath August Update
Our two storey entrance lobby is now visible as you walk along Redpath Avenue. take a look at the rendering of our Redpath facade and you can see how things are taking shape. We are now up to the 7th floor and should be adding a floor a week for the next few months.
293 Kingsway Condos
293 Kingsway Condo Update We have completed the concrete construction for levels 2 and 3 in the parking garage. The P1 garage level is scheduled to be completed by the end of July. We are currently pouring the columns and walls for the ground floor of the project.
July Update
Happy Canada Day everyone! Our building at 71 Redpath is really starting to take shape. Take a look at our views from the lower floors, which will just keep getting better as we reach the top. We are looking forward to this time next year when our residents will be enjoying our incredible rooftop pool and the other […]
June Update
We are moving on up! The 4th floor of the tower will soon be completed. Now that we are starting more typical floor layouts, we anticipate that we will be able to pour a floor every week, so check in regularly as we reach for the top. Although not visible , our parking garage is […]
May Redpath update
We are close to reaching our typical floor plates (from 4-18) and expect those floors to progress with increasing productivity. Our hoarding is now complete and finishing touches being made to our marketing materials for the hoarding and our new website, which will be released next month, stay tuned!
April Redpath Update
With the ground floor completed and the warmer weather in sight, we look forward to completing level 2 and progressing to level 3 this month.
March 1st Redpath Update
We finally have hit the ground floor of 71 Redpath! Final concrete for the ground floor and columns for the second floor are underway. We look forward to continuing our way to the top before the end of the year.
Redpath Update 68
Preparation for first Ground floor pour is underway. P1, exterior walls, water proofing nearing completion Completing exterior walls from P1 – Ground
Redpath Update 67
Continuing to Pour P1 Pouring P1 exterior walls