Waterproofing P2 exterior walls Completing pouring P2 Starting to deck for P1 Preparing for P2 exterior walls after waterproofing
Monthly Archives: November 2020
Redpath Update 61
Pouring P3 exterior walls, and columns Preparing to pour P2 Decking for P1 to go up in preparation for steel work
Redpath update 60
P3 ramp has been completed Steel work continues for P2 Preparing to pour P2
Kingsway Update 11
Condo Temporary ramp to be completed. Crane Pad to be dug Continuing to haul out spoils Rental Beginning underground drainage for Building B Pouring Elevator and Stair Pad for Building B Building A Stair Pad and Elevator to be dug out.
Kingsway Update 10
Condo Continuing to haul out soil. Crane Pad to be installed in preparation. Rentals Continuing concrete footings and columns for Building A. The Crane for Building A has been Erected. Beginning underground drains on building B. Digging elevator footing on Building B.
Redpath Update 59
Large section of P3 have been poured Continuing to waterproof P3 walls Decking for P2 is in the process of being erected
RP Update 58
Torching out Corner Braces and Whalers Continuing the pour of P3 Preparation for P2 Columns and Exterior walls being poured for P3,P2
Kingsway Update 9
Condo Beginning to dismantle dewatering system Continuing the cut to sub grade Rental Beginning backfill at interior footings on Building B Starting to pour footings for Building A Begging underground drain preparation for Building B Crane for Building A to be operational