Skip to content

293 Kingsway

Just another WordPress site

Monthly Archives: November 2020

Redpath Update 62

Waterproofing P2 exterior walls Completing pouring P2 Starting to deck for P1 Preparing for P2 exterior walls after waterproofing

Posted byadminNovember 30, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath Update 62

Redpath Update 61

Pouring P3 exterior walls, and columns Preparing to pour P2 Decking for P1 to go up in preparation for steel work

Posted byadminNovember 23, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath Update 61

Redpath update 60

P3 ramp has been completed Steel work continues for P2 Preparing to pour P2

Posted byadminNovember 16, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath update 60

Kingsway Update 11

Condo Temporary ramp to be completed. Crane Pad to be dug Continuing to haul out spoils Rental Beginning underground drainage for Building B Pouring Elevator and Stair Pad for Building B Building A Stair Pad and Elevator to be dug out.

Posted byadminNovember 16, 2020July 23, 2021Posted inKingswayLeave a comment on Kingsway Update 11

Kingsway Update 10

Condo Continuing to haul out soil. Crane Pad to be installed in preparation. Rentals Continuing concrete footings and columns for Building A. The Crane for Building A has been Erected. Beginning underground drains on building B. Digging elevator footing on Building B.

Posted byadminNovember 9, 2020November 9, 2020Posted inKingswayLeave a comment on Kingsway Update 10

Redpath Update 59

Large section of P3 have been poured Continuing to waterproof P3 walls Decking for P2 is in the process of being erected

Posted byadminNovember 9, 2020December 8, 2020Posted inRedpathLeave a comment on Redpath Update 59

RP Update 58

Torching out Corner Braces and Whalers Continuing the pour of P3 Preparation for P2 Columns and Exterior walls being poured for P3,P2

Posted byadminNovember 2, 2020November 9, 2020Posted inRedpathLeave a comment on RP Update 58

Kingsway Update 9

Condo Beginning to dismantle dewatering system Continuing the cut to sub grade Rental Beginning backfill at interior footings on Building B Starting to pour footings for Building A Begging underground drain preparation for Building B Crane for Building A to be operational

Posted byadminNovember 2, 2020November 9, 2020Posted inKingswayLeave a comment on Kingsway Update 9

Recent Posts

  • Kingsway Update
  • 71 Redpath August Update
  • 293 Kingsway Condos
  • July Update
  • June Update

Recent Comments

    Archives

    • August 2021
    • July 2021
    • June 2021
    • May 2021
    • April 2021
    • March 2021
    • February 2021
    • January 2021
    • December 2020
    • November 2020
    • October 2020
    • September 2020
    • August 2020
    • July 2020
    • June 2020
    • May 2020
    • April 2020
    • March 2020
    • February 2020
    • January 2020
    • December 2019
    • November 2019
    • October 2019
    • September 2019

    Categories

    • Kingsway
    • Redpath
    • Uncategorized

    Meta

    • Log in
    • Entries feed
    • Comments feed
    • WordPress.org
    293 Kingsway, Proudly powered by WordPress.