Excavation has been completed.
Monthly Archives: July 2020
RP Update 45
We are now one week away from completing our excavation. Waterproofing of the site has now begun and will continue for the 3 – 4 months, Construction of footings has now also begun, along with the early stages of the building foundation.
RP Update 44
Excavating and shoring continue as scheduled. Our mobile crane has now been delivered and is operating on site.
RP Update 43
Excavation and shoring continue as scheduled. This week, we will reach the lowest point of our excavation. Next week on Monday, Redpath Ave. will be limited to local traffic only between Soudan and Eglinton, as we have a crane delivery scheduled.