Monthly Archives: October 2019
RP Update 6
New fencing has been erected around our site, including a delineation setting the boundaries of our onsite parkland dedication The site is now being prepared for the shoring drilling equipment
RP Update 5
Demolition is now complete Shale is being brought onsite to backfill the voids left from demolishing the house foundations Once all backfilling is complete, the site will be graded in preparation for the beginning of shoring
RP Update 4
All houses have now been demolished Work continues on removing the house foundations and cleaning the site up in preparation for shoring and excavation Shoring is expected to begin next week
RP Update 3
Demolition is progressing on schedule, with over half of the houses making up the new project site now demolished Placement of the temporary fencing surrounding the site has been adjusted to allow for an even greater setback from the sidewalk and better visibility for turning cars at the corner of Soudan and Redpath